Village of Rye Brook, NY

Roadmap

showPermitting Process

2 of 14 Goals In Progress
6 of 14 Goals Achieved
43%7%
Planned

[P1-NY] Adopt the NY State Unified Solar Permit(7)

There is a standard building permit application form, but nothing specific to PV currently

Considering adoption of the NYS Unified Permit Form

Consider adopting a standard application form specific to solar PV for qualifying projects under 10kW.

[P2] Make Permit Application Form Available Online(176)

Permit application forms are available are online

Village currently at best practice. If a standard PV application form is adopted per goal [P1], make the form available online in an easily accessible location.

[P3] Allow Electronic Submittal of Application Form(87)

Original, hard copies are currently required in person

Allow email submittal of permit application forms for standard, qualifying projects.

[P4] Require only 1 Permit Application Submittal(164)

Only a single submittal is required.

[P5] Post Permit and Inspection Process Information and Fee Schedules Online(80)

Permit process information including point-of-contact and fee schedule is available online

[P6] Streamline Permit Processing Time and Allow Expedited Process for Qualifying Projects(75)

Permit turnaround normally takes more than two weeks

Consider an expedited or over-the-counter permit approval process for qualifying PV projects using a standard application form, particularly if the NYS Unified Solar Permit Form is adopted per goal [P1].

[P7] Base Residential Permit Fee on Actual Cost to Administer(85)

Permit fee is valuation based at $15/$1000 plus a flat fee for certificate of occupancy

The permit fee for a typical residential system would be around $375 for the building permit plus $150 for the certificate of occupancy. Total cost $525. This is a bit high for residential systems; consider capping the permit fee portion at a lower level.

[P8] Base Commercial Permit Fee on Actual Cost to Administer(55)

Permit fee is valuation based at $20/$1000 plus a flat fee of $650 for certificate of occupancy

Valuation based fee will become cost prohibitive for larger commercial systems. Consider basing the commercial permit fee on cost recovery or capping the valuation based fee.

[P9] Minimize Inspection Turnaround Time(147)

Inspection process normally takes more than two weeks

Applicants seeking an exterior building permit must first obtain approval from the Village of Rye Brook Architectural Review Board (ARB), which takes time. Consider a set of criteria, such as systems not visible from the street or systems flush mount to a roof, under which ARB review would not be necessary.

[P10] Offer Convenient Inspection Scheduling(94)

A specific appointment time is provided

[P11] Require only 1 Inspection Visit(82)

Preliminary inspection required after roof penetrations in addition to final inspection

Only a final inspection is required

[P12] Adopt an Inspection Checklist(21)

Survey response indicated a checklist is in use, but did not see online. Need to verify.

Utilize a standard inspection checklist for PV systems. The checklist serves as a guide for inspectors and installers containing points of emphasis and common issues. Ideally this is a regional document.

[P13] Allow a Structural Exemption for Qualifying Systems(41)

A structural PE stamp is currently required for both residential and commercial systems.

For qualifying residential systems on code approved residences meeting certain criteria, consider allowing an exemption from structural analysis or structural PE stamp requirements. This follows the guidance in the Unified Solar Permit, where an exemption from the PE letter is allowed if checklist questions #11-13 are satisfied and if the installation uses an engineered racking system.

[P14] Understand New Solar-Specific Building, Electrical, and Fire Codes(82)

Current codes are the 2008 NEC and state codes based on the 2009 ICC

Though a couple code cycles behind, building officials seem knowledgeable on current solar standards. For ongoing education, see the links under the 'Take Action' button at right.

showPlanning & Zoning

2 of 5 Goals Achieved
40%
Planned

[Z1] Pursue Protection for Solar Rights and Access(72)

State law allows for creation of solar easements and solar access provisions in local zoning code

Consider creating local ordinances which would protect solar access by ensuring property remains shade-free and establishing a process for creating, registering, and enforcing solar easements.

[Z2] Promote Solar Ready Construction via Ordinances or Building Codes(15)

Code encourages new streets to be oriented east-west to promote solar exposure

The existing Code is a great start, though consider further measures to create solar ready homes. See examples under the 'Take Action' button at right of additional no- to low- cost measures that can make it easier to retrofit solar.

[Z4] Incorporate Solar Priorities into Comprehensive or Energy Action Plans(66)

Village does have energy goals in long term planning

Both the Comprehensive Plan (2013-2014) and the Vision Plan Implementation Task Force (2004) include energy provisions. Consider including more solar specific goals in future updates; the Solar Roadmap team can help with model standards and language.

[Z5] Update Zoning Standards and Review for Solar Installations(92)

Solar is "as of right" in all zoning districts, though approval from Architectural Review Board is required

[Z7] Limit Impact of Restrictive Private Covenants(81)

Unknown whether local HOAs have any restrictive policies. To be determined.

Work with condo owner and homeowners associations to ensure that their covenant, conditions, and restrictions and bylaws do not create undue barriers to solar installations.

showFinancing Options

1 of 3 Goals Achieved
33%
Planned

[F5a] Explore Implementation of Local PACE Financing Pilot Program (73)

Rye Brook Village uses Town of Rye assessment rolls. Therefore, Energize Finance (PACE) would only be available if Town of Rye joins EIC as member.

Encourage the Town to take action on this issue. Joining the Energy Improvement Corporation (EIC) is a relatively simple process. Learn more here: http://energizeny.org/eic

[F6] Encourage Local Financial Stakeholders to Establish New Solar Loan Programs(63)

Local vendors offer 3rd party finance, and NYSERDA Green Jobs Green NY offers low interest loans

Effective finance options are offered in the region.

[F7] Promote Availability of Existing Solar Finance Options and Evaluation Tools(38)

Some awareness exists within the community currently

Publicize the availability of local solar finance options and solar evaluation tools for potential buyers. Consider doing this via an update to the existing webpage promoting the Solarize campaign, or by linking more visibly to the Village's participation in Sustainable Westchester which has many resources available.

showSolar Market Development

2 of 5 Goals In Progress
4 of 5 Goals Achieved
80%20%
Planned

[M1] Support Aggregate Procurement Program for Residential Sector(40)

Village has not participated in any such programs to date

Village joined the Solarize Westchester program and was selected in Round 2

Solarize Westchester has selected the Village of Rye Brook to participate in a solar discount program that makes installing solar electric systems simpler and more affordable for their residents and businesses. The Solarize Rye Brook program launched with a workshop on October 22, 2015 at the Rye Brook Village Hall which was open to homeowners and commercial property owners. Learn more at http://www.ryebrook.org/Cit-e-Access/webpage.cfm?TID=31&TPID=15455

[M3] Explore Implementation of Collaborative Procurement Program for Municipal Facilities and Schools(38)

Village joined the Municipal Solar Buyers Group

Village currently at best practice. The Buyers Group is an aggregation effort to allow public sector building access to solar installations via power purchase agreements.

[M6] Explore Installing Solar at Municipal Facilities, Including Landfill and Water Treatment Facilities(62)

Not aware of solar at any Village properties currently, though see goal [M3] for current activity

Establish a working group to identify solar feasibility at landfills, water treatment plants, or other municipal properties though the Solar Buyers Group. If there are additional properties that were not included in this RFP, the Solar Roadmap team can help by evaluating solar potential at these properties.

[M8] Provide Solar Educational Resources to Constituents(77)

Village does promote the Solarize program on their website. See details under goal [M1].

Village has taken great strides via participation in Sustainable Westchester and by promoting the local Solarize campaign.

[M10] Explore Joining Clean Energy Action and Recognition Programs(42)

Village is a member of Sustainable Westchester